User Tools

Site Tools


venus-os:gx_solaredge

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
venus-os:gx_solaredge [2020-10-13 18:32] – [3. How to configure Frequency Shifting] fjlacockvenus-os:gx_solaredge [2021-09-21 16:22] (current) – [5 How to configure Sunspec to allow inverter monitoring via Victron GX device] fjlacock
Line 11: Line 11:
  
 The AC coupled system sizing guideline, Factor 1.0 rule, from Victron Energy for AC coupled system must be adhered to. The AC coupled system sizing guideline, Factor 1.0 rule, from Victron Energy for AC coupled system must be adhered to.
 +
 +**Note**
 +
 +This APS feature is only available for 3phase and 1phase HDwave inverters.
  
 ===== 2. How to configure APS mode ===== ===== 2. How to configure APS mode =====
Line 181: Line 185:
 ;#; ;#;
  
-__Note:__ +**__Note:__
-For inverters with a screen, in addition to the settings above it is important to contact SolarEdge Support to change a parameter in the backend to allow the frequency shifting with APS mode.+
  
-For SetApp inverters with Firmware 4.10.xx or higher, the backend parameter will enable automatically.+In addition to the settings above it is important to contact SolarEdge Support to change a parameter in the backend to allow the frequency shifting with APS mode.**
  
  
Line 277: Line 280:
 **Note:**  **Note:** 
 It also advised editing the SolarEdge inverter’s IP address to a static IP by disabling DHCP edit the desired IP address for your SolarEdge inverter and the search for the IP address on your DX Device. The SolarEdge inverter will appear on you GX devices screen It also advised editing the SolarEdge inverter’s IP address to a static IP by disabling DHCP edit the desired IP address for your SolarEdge inverter and the search for the IP address on your DX Device. The SolarEdge inverter will appear on you GX devices screen
 +
 +
 +===== 6 For multiple SolarEdge inverter integration =====
 +
 +  - The SolarEdge inverter needs to be interconnected via RS485-1, with a Leader, follower configuration.
 +  - Only the Leader SolarEdge inverter requires the dry-relay contact connection. (section 1)
 +  - Only the Leader SolarEdge inverter requires the GPIO setting to Alternative Power Source configuration. (section 2)
 +  - Enable Grid Control for all the SolarEdge inverters on site. (Power control -> Grid Control -> Enable)
 +  - Setup the frequency shifting bandwidth for all the SolarEdge inverters on site. (section 3)
 +  - Each inverter requires its own TCP connection and IP address with the same SunSpec setting for each inverter. (Section 5)
  
venus-os/gx_solaredge.1602606760.txt.gz · Last modified: 2020-10-13 18:32 by fjlacock

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki