==== Err 2 - Battery voltage too high ==== | ==== Err 2 - Battery voltage too high ==== | ||
+ | |||
This error will auto-reset after the battery voltage has dropped. | This error will auto-reset after the battery voltage has dropped. | ||
This error can be due to other charging equipment connected to the battery or a fault in the charge controller. | This error can be due to other charging equipment connected to the battery or a fault in the charge controller. | ||
- | This error can also occur if the battery voltage is set to a lower voltage than the actual | + | This error can also occur if the battery voltage |
==== Err 3, Err 4 - Remote temperature sensor failure ==== | ==== Err 3, Err 4 - Remote temperature sensor failure ==== | ||
Check if the T-sense connector is properly connected to a remote temperature sensor. | Check if the T-sense connector is properly connected to a remote temperature sensor. | ||
Line 90: | Line 91: | ||
Error recovery: | Error recovery: | ||
* Error 38: First disconnect the solar panels and disconnect the battery. Wait for 3 minutes, then reconnect the battery first and next the panels. | * Error 38: First disconnect the solar panels and disconnect the battery. Wait for 3 minutes, then reconnect the battery first and next the panels. | ||
- | * Error 39: The charger will automatically resume operation once the battery voltage drops below the float level for 1 minute. | + | * Error 39: The charger will automatically resume operation once the battery voltage drops below its maximum voltage setting (normally Equalisation or Absorption voltages), for 250V versions or float voltage |
If the error persists the charge controller is probably faulty. | If the error persists the charge controller is probably faulty. | ||
+ | |||
+ | ==== Err 40 - PV Input failed to shutdown ==== | ||
+ | |||
+ | If the charger is unable to turn off the PV input, it will go into a safe mode in order to protect the battery from over-charging or having a high voltage on the battery terminals. In order to do that, the charger will stop charging and disconnect its own output. The charger will become faulty. | ||
==== Information 65 - Communication warning ==== | ==== Information 65 - Communication warning ==== | ||
Line 105: | Line 110: | ||
==== Err 67 - BMS Connection lost ==== | ==== Err 67 - BMS Connection lost ==== | ||
The charger is configured to be controlled by a BMS, but it does not receive any control messages from a BMS. The charger stopped charging, as a safety precaution. | The charger is configured to be controlled by a BMS, but it does not receive any control messages from a BMS. The charger stopped charging, as a safety precaution. | ||
+ | |||
+ | This Error only shows when there is solar power available and thus the Solarcharger is ready to initiate charging. It does not show at night. And in case there is a permanent problem, the error will raise in the morning and clear at night, and so forth. | ||
Check the connection between the charger and the BMS. | Check the connection between the charger and the BMS. | ||
- | __How to reset the charger, to de-couple it from the BMS__ | + | __How to reconfigure |
- | When the charger needs to operate in stand-alone mode again, not controlled by a BMS, it needs to be reset: | + | Our Chargers and Solarchargers automatically configure themselves to be BMS-controlled when they are connected to one; either direct or via a GX Device. And that setting is semi-permanent: |
+ | |||
+ | Here is what needs to be done to make the charger | ||
* VE.Can solar chargers, go into the setup menu, and change setting ‘BMS’ from ‘Y’ to ‘N’ (setup item 31). | * VE.Can solar chargers, go into the setup menu, and change setting ‘BMS’ from ‘Y’ to ‘N’ (setup item 31). | ||
* VE.Direct solar chargers, reset the charger to factory defaults with VictronConnect, | * VE.Direct solar chargers, reset the charger to factory defaults with VictronConnect, | ||
- | |||
- | Note that (solar-)chargers automatically configure themselves to be BMS-controlled when they are connected to one; either direct or via a Color Control GX or Venus GX. | ||
==== Err 68 - Network misconfigured ==== | ==== Err 68 - Network misconfigured ==== | ||
+ | Applies to SmartSolar/ | ||
- | The charger detects multiple conflicting network sources trying to take control of the charger. | + | To clear the error on the SmartSolar VE.Direct MPPTs update the FW version |
- | + | ||
- | Applies | + | |
- | The typical reason for the error to show is that the charger is configured to operate in parallel using our [[https:// | + | To clear the error on the SmartSolar/BlueSolar MPPTs VE.Can, update |
- | Resolution: disable the parallel operation by connecting VictronConnect, | + | __Background__ |
- | For SmartSolar MPPT VE.Can only, also make sure its not connected | + | Error 68 indicates that the charger detects multiple conflicting network sources, with the same priority, trying |
- | Once the conflict | + | Having a higher priority level means that, if the same information (e.g. Battery voltage sense) |
+ | Now, if the same information is being received from two interfaces that have the same priority level (as VE.Can and VE.Direct), the charger does not know how to prioritize those, causing error 68 to be triggered. | ||
Line 153: | Line 160: | ||
- Reconfigure the charger. | - Reconfigure the charger. | ||
+ | Please do report this to your Victron dealer and ask him to escalate it to Victron; as this error should never happen. Preferably include firmware version and any other specifics (VRM URL, VictronConnect screenshots or similar). | ||