ess:design-installation-manual [2020-07-29 13:42] guy_stewartess:design-installation-manual [2020-08-03 23:57] – [4.3 GX device - ESS Settings] simonhackett
Line 347: Line 347:
   * Victron 12.8V Lithium batteries, and other lithium batteries that have passive cell balancing   * Victron 12.8V Lithium batteries, and other lithium batteries that have passive cell balancing
  
-Because it makes no sense to leave a battery discharged, without reserve power in case of mains failure, we recommend leaving BatteryLife enabled on the following battery technologiestoo:+Because it makes no sense to leave a battery discharged, without reserve power in case of mains failure, we recommend leaving BatteryLife enabled for systems using Lithium with active cell balancinghowever it //can// be disabled in this case. 
  
-  * Lithium with active cell balancing +Redflow specifies that BatteryLife should be disabled in [[battery_compatibility:redflow_zcell|Redflow ZCell]] installationsbecause the ZCell battery can rest at zero SoC without damage for an unlimited period, and also because the BatteryLife function conflicts with the ZCell battery maintenance cycle.
-  * [[battery_compatibility:redflow_zcell|Redflow ZCell]]  +
- +
-HoweverBatteryLife //can// be disabled in these cases.+
  
 === 4.3.2 Grid meter installed === === 4.3.2 Grid meter installed ===
Line 693: Line 690:
  
 (Make sure you install the ESS on L1. If it's installed on another phase the visualisation will be wrong.) (Make sure you install the ESS on L1. If it's installed on another phase the visualisation will be wrong.)
-==== 7.Three-phase ESS ====+==== 7.Three-phase ESS ====
  
 A three-phase ESS system has at least one Multi installed on each phase. We recommend leaving the phase-compensation setting to its default: enabled. A three-phase ESS system has at least one Multi installed on each phase. We recommend leaving the phase-compensation setting to its default: enabled.
Line 953: Line 950:
   - Now check MPPT Charge Voltage Setpoint. It is supposed to be above actual battery voltage.   - Now check MPPT Charge Voltage Setpoint. It is supposed to be above actual battery voltage.
  
-Note that those last two set points are determined by software; and calculated based on the setpoints sent by the (CANbus connected) lithium battery: you can'change change them manually. Looking at them however does help understanding why certain things are happening;+Note that those last two set points are determined by software; and calculated based on the setpoints sent by the (CANbus connected) lithium battery: you can't change them manually. Looking at them however does help understanding why certain things are happening;