ve.bus:grid-codes-and-loss-of-mains-detection
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revisionNext revisionBoth sides next revision | ||
ve.bus:grid-codes-and-loss-of-mains-detection [2019-01-21 11:12] – [DISQUS] ictbeheer | ve.bus:grid-codes-and-loss-of-mains-detection [2019-09-13 15:50] – [How does LOM detection relate to overload shutdowns?] marmour | ||
---|---|---|---|
Line 20: | Line 20: | ||
==== How does LOM detection relate to overload shutdowns? ==== | ==== How does LOM detection relate to overload shutdowns? ==== | ||
- | To detect a loss of mains, the inverter/ | + | To detect a loss of mains, the inverter/ |
When connected to a generator, or to a grid with a long extension cable or long ‘last mile’ cable, the pushing and pulling on the grid does create high currents, and as a result the inverter/ | When connected to a generator, or to a grid with a long extension cable or long ‘last mile’ cable, the pushing and pulling on the grid does create high currents, and as a result the inverter/ | ||
Line 83: | Line 83: | ||
A: Yes, also in this case LOM is required to make for a safe and also local regulations compliant system. Running ESS with disabled-feed-back is still not the same as using a Multi in its default configuration without ESS. | A: Yes, also in this case LOM is required to make for a safe and also local regulations compliant system. Running ESS with disabled-feed-back is still not the same as using a Multi in its default configuration without ESS. | ||
+ | |||
+ | ===== DISQUS ===== | ||
+ | ~~DISQUS~~ | ||
ve.bus/grid-codes-and-loss-of-mains-detection.txt · Last modified: 2022-10-31 23:41 by mvader